United States › Grid › Interconnection queues › Connecticut

GAS · ISO-NE

Fuel Cell

Fuel Cell is a 14.4 MW gas request built and operating in the ISO-NE interconnection queue, in New Haven County, Connecticut, connecting to UI.

Queue statusOperating
  1. PlanningQueued Aug 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1055
Grid region
ISO-NE (New England)
Utility / transmission owner
UI
Connection point (POI)
UI 13.8kV Indian Well Substation
Location
New Haven County, Connecticut
Technology
Gas: 14.4 MW
Total requested
14.4 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
26 August 2020
Proposed online date
December 2023

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut