United States › Grid › Interconnection queues › Massachusetts
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 168 MW battery storage request in interconnection study in the ISO-NE interconnection queue, in Bristol County, Massachusetts.
- PlanningQueued Jun 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 1412
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Direct tap into the Pottersville Substation in Somerset, MA
- Location
- Bristol County, Massachusetts
- Technology
- Battery: 168 MW
- Total requested
- 168 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 20 June 2023
- Proposed online date
- September 2027
Location
Marker shows the centre of Bristol County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Bristol County
- Battery StorageBattery storage · 350 MW · in study
- Brayton Point 3 Uprate( see 243)Coal · 30.0 MW · built
- Dartmouth Power ExpansionGas · 24.0 MW · built
- Increase to Steam Turbine Capacity Uprate (See QPCoal · 6.0 MW · built
- Dighton Power UprateGas · 5.0 MW · built
- SolarSolar · 1.9 MW · built
- Combined CycleGas · 550 MW · withdrawn
- Battery StorageBattery storage · 529 MW · withdrawn
- Battery StorageBattery storage · 293 MW · withdrawn
- Battery StorageBattery storage · 271 MW · withdrawn
- Battery StorageBattery storage · 257 MW · withdrawn
- Energy StorageBattery storage · 246 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem