COAL · ISO-NE

Increase to Steam Turbine Capacity Uprate (See QP

Increase to Steam Turbine Capacity Uprate (See QP is a 6.0 MW coal request built and operating in the ISO-NE interconnection queue, in Bristol County, Massachusetts.

Queue statusOperating
  1. PlanningQueued Jan 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
243
Grid region
ISO-NE (New England)
Connection point (POI)
Brayton Point 345 kV Switchyard
Location
Bristol County, Massachusetts
Technology
Coal: 6.0 MW
Total requested
6.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
4 January 2008
Proposed online date
December 2011

Location

Marker shows the centre of Bristol County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Bristol County