United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 271 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1367
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid 115KV Line U6 between Pottersville and Bridgewater substations - approximately 6.1 circuit miles from Bridgewater substation
Location
Bristol County, Massachusetts
Technology
Battery: 271 MW
Total requested
271 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
9 March 2023
Proposed online date
April 2027
Withdrawn
November 2023

Location

Marker shows the centre of Bristol County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Bristol County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem