United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
GAS Β· ISO-NECombined Cycle
Combined Cycle is a 550 MW gas request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2007 (completed)
- Withdrawn / abandonedNov 2007 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 211
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NSTAR 115 kV line #111
- Location
- Bristol County, Massachusetts
- Technology
- Gas: 550 MW Β· Oil
- Total requested
- 550 MW
- Service type
- Other
- Queue status
- Withdrawn
- Entered queue
- 8 May 2007
- Proposed online date
- June 2010
- Withdrawn
- November 2007
Location
Marker shows the centre of Bristol County; the queue data does not give exact sites.
Power plants in Massachusetts Β· Transmission lines in Massachusetts
Other requests in Bristol County
- Battery StorageBattery storage Β· 350 MW Β· in study
- Battery StorageBattery storage Β· 168 MW Β· in study
- Brayton Point 3 Uprate( see 243)Coal Β· 30.0 MW Β· built
- Dartmouth Power ExpansionGas Β· 24.0 MW Β· built
- Increase to Steam Turbine Capacity Uprate (See QPCoal Β· 6.0 MW Β· built
- Dighton Power UprateGas Β· 5.0 MW Β· built
- SolarSolar Β· 1.9 MW Β· built
- Battery StorageBattery storage Β· 529 MW Β· withdrawn
- Battery StorageBattery storage Β· 293 MW Β· withdrawn
- Battery StorageBattery storage Β· 271 MW Β· withdrawn
- Battery StorageBattery storage Β· 257 MW Β· withdrawn
- Energy StorageBattery storage Β· 246 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem