🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Mississippi

GAS · MISO

Lakeover CCCT

Lakeover CCCT is a 820 MW gas request in interconnection study in the MISO interconnection queue, in Hinds County, Mississippi, connecting to Entergy Mississippi, LLC.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0047
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy Mississippi, LLC
Developer
Entergy Mississippi, LLC
Connection point (POI)
Green Acres 230kV (new)
Location
Hinds County, Mississippi
Technology
Gas: 820 MW
Total requested
820 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
August 2028

Location

Marker shows the centre of Hinds County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Hinds County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem