United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
GAS Β· MISOGas project J3825, Hinds County
Gas project J3825, Hinds County is a 770 MW gas request withdrawn in the MISO interconnection queue, in Hinds County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3825
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI, LLC.
- Connection point (POI)
- 230kV Greenacres Substation
- Location
- Hinds County, Mississippi
- Technology
- Gas: 770 MW
- Total requested
- 770 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- January 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Hinds County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Hinds County
- Solar project J1672, Hinds CountySolar Β· 150 MW Β· agreement signed
- Lakeover CCCTGas Β· 820 MW Β· in study
- Solar + storage project J2173, Hinds CountySolar + storage Β· 396 MW Β· in study
- Gas project J477, Hinds CountyGas Β· 36.4 MW Β· built
- Solar project J2595, Hinds CountySolar Β· 650 MW Β· withdrawn
- Solar project J2594, Hinds CountySolar Β· 650 MW Β· withdrawn
- Solar project J1640, Hinds CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project J2827, Hinds CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project J910, Hinds CountySolar Β· 150 MW Β· withdrawn
- Solar + storage project J3062, Hinds CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project J1136, Hinds CountySolar Β· 100 MW Β· withdrawn
- Solar project J2370, Hinds CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem