United States › Grid › Interconnection queues › Louisiana
GAS · MISOGas project J4133, De Soto Parish County
Gas project J4133, De Soto Parish County is a 756 MW gas request in interconnection study in the MISO interconnection queue, in De Soto Parish County, Louisiana, connecting to CLECO POWER.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4133
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Dolet Hills Substation
- Location
- De Soto Parish County, Louisiana
- Technology
- Gas: 756 MW
- Total requested
- 756 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 3 October 2025
- Proposed online date
- June 2030
Location
Marker shows the centre of De Soto Parish County; the queue data does not give exact sites.
Other requests in De Soto Parish County
- Replace 330 MW of CLECO.DPS Unit with solar; Dolet HillsOther · 330 MW · in study
- Solar project J2208, De Soto Parish CountySolar · 99.0 MW · in study
- Solar project J3180, De Soto Parish CountySolar · 110 MW · withdrawn
- Solar project GEN-2022-108, Desoto Parish CountySolar · 100 MW · withdrawn
- Solar project J2411, De Soto Parish CountySolar · 80.0 MW · withdrawn
- Battery storage project J3178, De Soto Parish CountyBattery storage · 50.0 MW · withdrawn
- Solar project GEN-2023-030, Desoto Parish CountySolar · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem