SOLAR Β· MISO

Solar project J3180, De Soto Parish County

Solar project J3180, De Soto Parish County is a 110 MW solar request withdrawn in the MISO interconnection queue, in De Soto Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3180
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Dolet Hills
Location
De Soto Parish County, Louisiana
Technology
Solar: 110 MW
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
October 2026
Withdrawn
July 2025

Location

Marker shows the centre of De Soto Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in De Soto Parish County