Gas project J3936, Kenosha County

Gas project J3936, Kenosha County is a 132 MW gas request in interconnection study in the MISO interconnection queue, in Kenosha County, Wisconsin, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3936
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
PARIS 345kV Substation
Location
Kenosha County, Wisconsin
Technology
Gas: 132 MW
Total requested
132 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
12 February 2025
Proposed online date
January 2027

Location

Marker shows the centre of Kenosha County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Kenosha County