BATTERY STORAGE · MISO

Battery storage project J3785, Kenosha County

Battery storage project J3785, Kenosha County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Kenosha County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3785
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Pleasant Prairie
Location
Kenosha County, Michigan
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 April 2024
Proposed online date
June 2028

Location

Marker shows the centre of Kenosha County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Kenosha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem