United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in the USA
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Jove Solar Solar + storage |
4,133 MW | In study |
| Solar + storage project G0822, Benton County Solar + storage |
4,000 MW | In study |
| Other project G0695, Crook County Other |
3,600 MW | In study |
| Schahfer CCGTs Gas · NIPSCO |
2,740 MW | In study |
| Solar + storage project Q2409, Navajo County Solar + storage |
2,626 MW | In study |
| Solar + storage project G1052, Deschutes County Solar + storage |
2,600 MW | In study |
| Solar + storage project G1051, Deschutes County Solar + storage |
2,600 MW | In study |
| Solar + storage project Q68, Los Angeles County Solar + storage |
2,400 MW | In study |
| Muon Solar + storage |
2,339 MW | In study |
| Gas project J3996, St. Charles County Gas |
2,220 MW | In study |
| Offshore wind project AI2-431, Atlantic County Offshore wind |
2,139 MW | In study |
| Gas project AG2-582, Doddridge County Gas · CPV Shay, LLC |
2,100 MW | In study |
| Offshore wind project AI1-001, Monmouth County Offshore wind |
2,100 MW | In study |
| Stanley Solar + storage |
2,071 MW | In study |
| Quark Solar + storage |
2,045 MW | In study |
| Bouse Solar And Storage Plant Solar + storage |
2,021 MW | In study |
| Solar + storage project Q255, Coconino County Solar + storage |
2,000 MW | In study |
| Solar + storage project G0681, Wasco County Solar + storage |
2,000 MW | In study |
| Smarr CC Gas |
2,000 MW | In study |
| Ripple Solar + storage |
1,880 MW | In study |
| Solar + storage project G0699, Crook County Solar + storage |
1,800 MW | In study |
| Other project G0675, Crook County Other |
1,800 MW | In study |
| Gas project 489, Roane County Gas |
1,689 MW | In study |
| Prairie Ridge (Gas - CC) Gas · Tenaska Power Generation, LLC |
1,660 MW | In study |
| Solar + storage project 660, Owyhee County Solar + storage · Sawtooth DevCo, LLC |
1,650 MW | Paused / redesign |
| Solar + storage project 659, Jerome County Solar + storage · Sawtooth DevCo, LLC |
1,650 MW | Paused / redesign |
| Solar + storage project Q92, San Bernardino County Solar + storage |
1,650 MW | In study |
| Richland Parish generators Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Richland Parish generators Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Franklin Farms Gas · Entergy Louisiana, LLC |
1,640 MW | In study |
| Gas project 977726, Rowan County Gas |
1,620 MW | In study |
| Gas project 483, Stewart County Gas |
1,600 MW | In study |
| Gas project 628, Todd County Gas |
1,600 MW | In study |
| Gas project 620, Trousdale County Gas |
1,600 MW | In study |
| Plum Solar + storage |
1,560 MW | In study |
| Hecate Energy Orem Wind Onshore wind · Hecate Energy LLC |
1,542 MW | In study |
| Gas project J3999, Vermillion County Gas |
1,540 MW | In study |
| Aegle Power Gas · Aegle Power LLC |
1,536 MW | In study |
| Gas project J4071, Livingston Parish County Gas |
1,500 MW | In study |
| Caldwell County Energy Center Gas · Caldwell County Energy Center, LLC |
1,500 MW | In study |
| Big Canyon Wind Onshore wind · Longfellow Wind, LLC |
1,500 MW | In study |
| Solar + storage project Q98, Los Angeles County Solar + storage |
1,500 MW | In study |
| Onshore wind project Q320, San Juan County Onshore wind |
1,500 MW | Paused / redesign |
| Gas project J4024, Monroe County Gas |
1,499 MW | In study |
| Gas project J4025, Monroe County Gas |
1,499 MW | In study |
| Gas project 958347, Person County Gas · Duke Energy Progress, LLC |
1,455 MW | In study |
| Gas project J3799, Livingston County Gas |
1,452 MW | In study |
| Gas project 957264, Anderson County Gas |
1,450 MW | In study |
| Gas project J3922, Branch County Gas |
1,445 MW | In study |
| Ranegras PVS Solar + storage |
1,438 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,496 · 455.6 GW
- ERCOT (Texas)1,408 · 328.0 GW
- MISO (Midcontinent)1,337 · 302.2 GW
- Southeast (non-ISO utilities)815 · 118.5 GW
- SPP (Southwest Power Pool)480 · 114.8 GW
- PJM (Mid-Atlantic, Midwest)905 · 105.4 GW
- CAISO (California)194 · 92.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)27 · 6,015 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)