United States › Grid › Interconnection queues › Tennessee
GAS · SOUTHEASTGas project 489, Roane County
Gas project 489, Roane County is a 1,689 MW gas request in interconnection study in the Southeast interconnection queue, in Roane County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusIn planning
- PlanningQueued Dec 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 489
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Kingston Fossil Plant
- Location
- Roane County, Tennessee
- Technology
- Gas: 1,689 MW
- Total requested
- 1,689 MW
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 9 December 2021
- Proposed online date
- June 2026
Location
Marker shows the centre of Roane County; the queue data does not give exact sites.
Other requests in Roane County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem