United States › Grid › Interconnection queues › Tennessee
BATTERY STORAGE · SOUTHEASTBattery storage project 547, Roane County
Battery storage project 547, Roane County is a 100 MW battery storage request in interconnection study in the Southeast interconnection queue, in Roane County, Tennessee, connecting to Tennessee Valley Authority.
- PlanningQueued Apr 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 547
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Kingston Steam Plant 161kV Switchayrd
- Location
- Roane County, Tennessee
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 17 April 2023
- Proposed online date
- December 2026
Location
Marker shows the centre of Roane County; the queue data does not give exact sites.
Other requests in Roane County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem