🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · WEST

Solar + storage project Q92, San Bernardino County

Solar + storage project Q92, San Bernardino County is a 1,650 MW solar + storage request in interconnection study in the West interconnection queue, in San Bernardino County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q92
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Adelanto 500 KV Switchyard
Location
San Bernardino County, California
Technology
Solar: 1,650 MW · Battery
Total requested
1,650 MW
Study phase
Application received
Queue status
Active
Entered queue
20 June 2022
Proposed online date
December 2025

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem