🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · CAISO

Bouse Solar And Storage Plant

Bouse Solar And Storage Plant is a 2,021 MW solar + storage request in interconnection study in the CAISO interconnection queue, in La Paz County, Arizona, connecting to SCE.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2033 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2052
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River - Palo Verde 500kV
Location
La Paz County, Arizona
Technology
Solar: 1,010 MW · Battery: 1,011 MW
Total requested
2,021 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
15 April 2021
Proposed online date
December 2033

Location

Marker shows the centre of La Paz County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in La Paz County