United States › Grid › Interconnection queues › Arizona
SOLAR + STORAGE · CAISOBlueWater Solar
BlueWater Solar is a 2,031 MW solar + storage request withdrawn in the CAISO interconnection queue, in La Paz County, Arizona, connecting to DCRT.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2023 (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 2292
- Grid region
- CAISO (California)
- Utility / transmission owner
- DCRT
- Connection point (POI)
- Cielo Azul
- Location
- La Paz County, Arizona
- Technology
- Solar: 1,016 MW · Battery: 1,014 MW
- Total requested
- 2,031 MW
- Service type
- Energy only (ERIS)
- Study phase
- Caiso Cluster 15 Unvalidated
- Queue status
- Withdrawn
- Entered queue
- 17 April 2023
- Proposed online date
- December 2028
- Withdrawn
- May 2025
Location
Marker shows the centre of La Paz County; the queue data does not give exact sites.
Other requests in La Paz County
- Atlas ComplexSolar + storage · 4,357 MW · agreement signed
- Centennial FlatsSolar + storage · 767 MW · agreement signed
- Jove SolarSolar + storage · 4,133 MW · in study
- Bouse Solar And Storage PlantSolar + storage · 2,021 MW · in study
- Ranegras PVSSolar + storage · 1,438 MW · in study
- Socorro Peak SolarSolar + storage · 756 MW · in study
- Gas project 2023-G13, La Paz CountyGas · 453 MW · in study
- Solar + storage project 2023-G9, La Paz CountySolar + storage · 250 MW · in study
- Solar + storage project 2022-G1, La Paz CountySolar + storage · 250 MW · in study
- Solar + storage project 2023-G8, La Paz CountySolar + storage · 250 MW · in study
- Adobe FlatsSolar + storage · 1,024 MW · withdrawn
- La PosaSolar · 900 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem