Centennial Flats

Centennial Flats is a 767 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in La Paz County, Arizona, connecting to DCRT.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1529
Grid region
CAISO (California)
Utility / transmission owner
DCRT
Connection point (POI)
Delaney-Colorado River 500 kV Line
Location
La Paz County, Arizona
Technology
Solar: 500 MW · Battery: 267 MW
Total requested
767 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
16 April 2018
Agreement signed
5 January 2023
Proposed online date
April 2026

Location

Marker shows the centre of La Paz County; the queue data does not give exact sites.