🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Idaho

SOLAR + STORAGE · WEST

Solar + storage project 654, Bingham County

Solar + storage project 654, Bingham County is a 130 MW solar + storage request suspended in the West interconnection queue, in Bingham County, Idaho, connecting to Idaho Power Company.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. ConsentedNov 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
654
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Pingree Solar LLC
Connection point (POI)
Pingree 138kV Substation
Location
Bingham County, Idaho
Technology
Solar: 130 MW · Battery
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Suspended
Entered queue
3 May 2022
Agreement signed
2 November 2023
Proposed online date
March 2028

Location

Marker shows the centre of Bingham County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Bingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem