United States › Grid › Interconnection queues › Idaho
SOLAR + STORAGE · WESTSolar + storage project 654, Bingham County
Solar + storage project 654, Bingham County is a 130 MW solar + storage request suspended in the West interconnection queue, in Bingham County, Idaho, connecting to Idaho Power Company.
Queue statusPaused / redesign
- PlanningQueued May 2022 (current stage)
- ConsentedNov 2023 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 654
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Pingree Solar LLC
- Connection point (POI)
- Pingree 138kV Substation
- Location
- Bingham County, Idaho
- Technology
- Solar: 130 MW · Battery
- Total requested
- 130 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Suspended
- Entered queue
- 3 May 2022
- Agreement signed
- 2 November 2023
- Proposed online date
- March 2028
Location
Marker shows the centre of Bingham County; the queue data does not give exact sites.
Other requests in Bingham County
- Solar + storage project T2-029, Bingham CountySolar + storage · 398 MW · in study
- Onshore wind project T2-025, Bingham CountyOnshore wind · 300 MW · in study
- Solar project 737, Bingham CountySolar · 280 MW · in study
- Onshore wind project C2-92, Bingham CountyOnshore wind · 206 MW · in study
- Onshore wind project 782, Bingham CountyOnshore wind · 199 MW · in study
- Solar + storage project 725, Bingham CountySolar + storage · 175 MW · in study
- Onshore wind project S0022, Bingham CountyOnshore wind · 152 MW · in study
- Nuclear project 788, Bingham CountyNuclear · 45.0 MW · in study
- Onshore wind project 255, Bingham CountyOnshore wind · 152 MW · built
- Onshore wind project TCS-47, Bingham CountyOnshore wind · 450 MW · withdrawn
- Onshore wind project 1172, Bingham CountyOnshore wind · 450 MW · withdrawn
- Onshore wind project C4-018, Bingham CountyOnshore wind · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem