United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

ONSHORE WIND Β· WEST

Onshore wind project TCS-47, Bingham County

Onshore wind project TCS-47, Bingham County is a 450 MW onshore wind request withdrawn in the West interconnection queue, in Bingham County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
TCS-47
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Goshen-Bonneville transmission line
Location
Bingham County, Idaho
Technology
Wind: 450 MW
Total requested
450 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
10 October 2019
Proposed online date
September 2023

Location

Marker shows the centre of Bingham County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Bingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem