🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown826200.1 GW
Active in queue200.1 GW826 requests
Agreement signed49.9 GW242 requests
Withdrawn4,524860.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

826 requests · page 1 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Hecate Energy Orem Wind
Onshore wind · Hecate Energy LLC
1,542 MWIn study Brazoria, TXERCOT Jun 2023target 2030
Big Canyon Wind
Onshore wind · Longfellow Wind, LLC
1,500 MWIn study Pecos, TXERCOT Jan 2025target 2031
Onshore wind project Q320, San Juan County
Onshore wind
1,500 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Corvette Wind
Onshore wind
1,200 MWPaused / redesign Carson, TXERCOT Feb 2024
Hecate Energy Arkansas Wind
Onshore wind · Hecate Energy Gulf Wind LLC
1,029 MWIn study San Patricio, TXERCOT Jun 2023target 2030
Hecate Energy Jamaica Wind
Onshore wind · Hecate Energy LLC
1,029 MWIn study Galveston, TXERCOT Jun 2023target 2030
Onshore wind project GI-83, Randolph County
Onshore wind
1,018 MWAgreement signed Randolph, MOSoutheast Jun 2019target 2027
Onshore wind project Q318, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project Q319, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Complex Serenity Wind
Onshore wind · Serenity Wind, LLC
971 MWIn study Armstrong, TXERCOT Jun 2025target 2029
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Axis Ridge Wind
Onshore wind · Axis Ridge Wind, LLC
750 MWIn study Sutton, TXERCOT Nov 2024target 2029
Onshore wind project 391
Onshore wind
750 MWPaused / redesign West Aug 2020target 2023
Onshore wind project 418, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jan 2022target 2026
Onshore wind project 356, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Onshore wind project C012, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jul 2020target 2023
Onshore wind project 357, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Buffalo Jump Wind
Onshore wind · BOULEVARD ASSOCIATES, LLC
740 MWIn study Culberson, TXERCOT Nov 2025target 2029
Onshore wind project Company MY, Lassen County
Onshore wind
715 MWPaused / redesign Lassen, CAWest Mar 2022target 2032
Meitner 2 Wind
Onshore wind · IP Meitner, LLC
709 MWIn study Gray, TXERCOT Jun 2025target 2028
Meitner Wind
Onshore wind · IP Meitner, LLC
709 MWAgreement signed Gray, TXERCOT Jul 2023target 2027
Commodus 2 Wind
Onshore wind · IP Blackwell II, LLC
642 MWIn study Swisher, TXERCOT Mar 2025target 2029
Commodus Wind
Onshore wind · IP Blackwell, LLC
641 MWIn study Briscoe, TXERCOT Jul 2024target 2029
Cavell Wind
Onshore wind · IP Cavell, LLC
641 MWIn study Castro, TXERCOT Jul 2024target 2029
Aurelius 3 Wind
Onshore wind · IP Roman III, LLC
623 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Aurelius 2 Wind
Onshore wind · IP Roman Wind II, LLC
622 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Aurelius Wind
Onshore wind · IP Roman Wind, LLC
622 MWAgreement signed Deaf Smith, TXERCOT Aug 2023target 2028
White Oak King Wind
Onshore wind · KSK Wind Farm 1, LLC
607 MWIn study King, TXERCOT Mar 2023target 2027
Kingsmill Wind SLF
Onshore wind · Kingsmill Wind, LLC
606 MWIn study Carson, TXERCOT Jan 2024target 2029
Onshore wind project 5RSC-2024-17, Kit Carson County
Onshore wind
603 MWIn study Kit Carson, COWest Jan 2024target 2026
Onshore wind project GI-2016-3, Lincoln County
Onshore wind
600 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Onshore wind project 366, Rosebud County
Onshore wind
600 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Onshore wind project C006, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Feb 2019target 2021
Onshore wind project GEN-2024-345, Nowata County
Onshore wind
600 MWIn study Nowata, OKSPP Mar 2025target 2030
Tehuacana Wind
Onshore wind
600 MWPaused / redesign Limestone, TXERCOT Jun 2017
Sitges Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
600 MWIn study Motley, TXERCOT Mar 2024target 2029
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Onshore wind project GEN-2016-119, Kingfisher County
Onshore wind
600 MWAgreement signed Kingfisher, OKSPP Nov 20162025
Onshore wind project G0953, Lincoln County
Onshore wind
600 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Dundee East A Wind
Onshore wind · Felix 2, LLC
524 MWAgreement signed Baylor, TXERCOT Jan 2023target 2027
Tall Saddle Wind
Onshore wind · Tall Saddle Wind, LLC
523 MWIn study Kenedy, TXERCOT Jul 2024target 2029
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project C1-35, Carbon County
Onshore wind · Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project NC5-008, Mohave County
Onshore wind
500 MWIn study Mohave, AZWest May 2021target 2025
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Onshore wind project G0861, Deschutes County
Onshore wind
500 MWIn study Deschutes, ORWest Apr 2023target 2027
Onshore wind project G0619, Wasco County
Onshore wind
500 MWIn study Wasco, ORWest Apr 2019target 2023
Page 1 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)