United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTKingsmill Wind SLF
Kingsmill Wind SLF is a 606 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Carson County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2024 (current stage)
- ConsentedDec 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0140
- Grid region
- ERCOT (Texas)
- Developer
- Kingsmill Wind, LLC
- Connection point (POI)
- 79005 Railhead 345kV
- Location
- Carson County, Texas
- Technology
- Wind: 606 MW
- Total requested
- 606 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 11 January 2024
- Agreement signed
- 18 December 2025
- Proposed online date
- September 2029
Location
Marker shows the centre of Carson County; the queue data does not give exact sites.
Other requests in Carson County
- Panhandle Flagship Solar 1Solar + storage · 439 MW · agreement signed
- Panhandle Flagship StorageSolar + storage · 372 MW · agreement signed
- Kota BatteryBattery storage · 201 MW · in study
- Corvette WindOnshore wind · 1,200 MW · suspended
- Grandview 4 Phase A WindOnshore wind · 201 MW · suspended
- Onshore wind project GEN-2003-020, Carson CountyOnshore wind · 159 MW · built
- Onshore wind project GEN-2016-070, Carson CountyOnshore wind · 5.3 MW · built
- Onshore wind project GEN-2003-021, Carson CountyOnshore wind · 400 MW · withdrawn
- Panhandle Wind 3Onshore wind · 248 MW · withdrawn
- Onshore wind project GEN-2004-003, Carson CountyOnshore wind · 240 MW · withdrawn
- Onshore wind project GEN-2003-008, Carson CountyOnshore wind · 240 MW · withdrawn
- Onshore wind project GEN-2003-015, Carson CountyOnshore wind · 240 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem