United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Panhandle Wind 3

Panhandle Wind 3 is a 248 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Carson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2012 (completed)
  2. Withdrawn / abandonedFeb 2022 (project stopped here)
  3. ConsentedAug 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0030c
Grid region
ERCOT (Texas)
Developer
PATTERN PANHANDLE WIND 3 LLC
Connection point (POI)
79005 Railhead 345kV
Location
Carson County, Texas
Technology
Wind: 248 MW
Total requested
248 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
2 July 2012
Agreement signed
25 August 2014
Proposed online date
December 2022
Withdrawn
February 2022

Location

Marker shows the centre of Carson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Carson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem