ONSHORE WIND · SPP

Onshore wind project GEN-2016-070, Carson County

Onshore wind project GEN-2016-070, Carson County is a 5.3 MW onshore wind request built and operating in the SPP interconnection queue, in Carson County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Mar 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-070
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Martin 115 kV Substation
Location
Carson County, Texas
Technology
Wind: 5.3 MW
Total requested
5.3 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 March 2016
Proposed online date
December 2020
Came online
December 2020

Location

Marker shows the centre of Carson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Carson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem