πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2003-021, Carson County

Onshore wind project GEN-2003-021, Carson County is a 400 MW onshore wind request withdrawn in the SPP interconnection queue, in Carson County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2003-021
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Location
Carson County, Texas
Technology
Wind: 400 MW
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 December 2003
Proposed online date
December 2004

Location

Marker shows the centre of Carson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Carson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem