ONSHORE WIND · WESTOnshore wind project 5RSC-2024-29, Yuma County
Onshore wind project 5RSC-2024-29, Yuma County is a 554 MW onshore wind request in interconnection study in the West interconnection queue, in Yuma County, Colorado, connecting to Public Service Company Of Colorado.
- PlanningQueued Jan 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 5RSC-2024-29
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Goose Creek-Canal Crossing 345 kV line
- Location
- Yuma County, Colorado
- Technology
- Wind: 554 MW
- Total requested
- 554 MW
- Service type
- Energy only (ERIS)
- Study phase
- Detailed status: Phase 1 study underway
- Queue status
- Active
- Entered queue
- 24 January 2024
- Proposed online date
- May 2027
Location
Marker shows the centre of Yuma County; the queue data does not give exact sites.
Other requests in Yuma County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem