Other project GI-CS-2025-29, Yuma County

Other project GI-CS-2025-29, Yuma County is a 300 MW other request in interconnection study in the West interconnection queue, in Yuma County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2031 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-CS-2025-29
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Burlington - Wray 230kV Line
Location
Yuma County, Colorado
Technology
Solar: 300 MW · Wind · Battery
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
6 October 2025
Proposed online date
August 2031

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Yuma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem