United States › Grid › Interconnection queues › Colorado
ONSHORE WIND · WESTOnshore wind project GI-TC-2024-12, Yuma County
Onshore wind project GI-TC-2024-12, Yuma County is a 170 MW onshore wind request in interconnection study in the West interconnection queue, in Yuma County, Colorado, connecting to Tri-State Generation and Transmission Association.
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-TC-2024-12
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Burlington-Wray 230kV Line
- Location
- Yuma County, Colorado
- Technology
- Wind: 170 MW
- Total requested
- 170 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 21 May 2024
- Proposed online date
- October 2027
Location
Marker shows the centre of Yuma County; the queue data does not give exact sites.
Other requests in Yuma County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem