ONSHORE WIND · SPPOnshore wind project GEN-2016-119, Kingfisher County
Onshore wind project GEN-2016-119, Kingfisher County is a 600 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Kingfisher County, Oklahoma, connecting to OGE.
Queue statusConsented
- PlanningQueued Nov 2016 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingDec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2016-119
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Spring Creek-Sooner 345kV
- Location
- Kingfisher County, Oklahoma
- Technology
- Wind: 600 MW
- Total requested
- 600 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 30 November 2016
- Proposed online date
- December 2025
- Came online
- December 2025
Location
Marker shows the centre of Kingfisher County; the queue data does not give exact sites.
Other requests in Kingfisher County
- Battery storage project GEN-2018-011, Kingfisher CountyBattery storage · 74.1 MW · agreement signed
- Battery storage project GEN-2024-062, Kingfisher CountyBattery storage · 230 MW · in study
- Onshore wind project GEN-2015-063, Kingfisher CountyOnshore wind · 300 MW · built
- Onshore wind project GEN-2016-118, Kingfisher CountyOnshore wind · 288 MW · built
- Onshore wind project GEN-2016-032, Kingfisher CountyOnshore wind · 200 MW · built
- Onshore wind project GEN-2008-134, Kingfisher CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GI-58, Kingfisher CountyOnshore wind · 200 MW · withdrawn
- Solar project GI-69, Kingfisher CountySolar · 105 MW · withdrawn
- Onshore wind project GEN-2008-107, Kingfisher CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project GEN-2008-106, Kingfisher CountyOnshore wind · 100 MW · withdrawn
- Solar project GEN-2017-238, Kingfisher CountySolar · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem