United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2018-011, Kingfisher County
Battery storage project GEN-2018-011, Kingfisher County is a 74.1 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Kingfisher County, Oklahoma, connecting to WFEC.
Queue statusConsented
- PlanningQueued Apr 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2018-011
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WFEC
- Connection point (POI)
- Dover 138 kV Switching Station
- Location
- Kingfisher County, Oklahoma
- Technology
- Battery: 74.1 MW
- Total requested
- 74.1 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 27 April 2018
- Proposed online date
- December 2027
Location
Marker shows the centre of Kingfisher County; the queue data does not give exact sites.
Other requests in Kingfisher County
- Onshore wind project GEN-2016-119, Kingfisher CountyOnshore wind · 600 MW · agreement signed
- Battery storage project GEN-2024-062, Kingfisher CountyBattery storage · 230 MW · in study
- Onshore wind project GEN-2015-063, Kingfisher CountyOnshore wind · 300 MW · built
- Onshore wind project GEN-2016-118, Kingfisher CountyOnshore wind · 288 MW · built
- Onshore wind project GEN-2016-032, Kingfisher CountyOnshore wind · 200 MW · built
- Onshore wind project GEN-2008-134, Kingfisher CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GI-58, Kingfisher CountyOnshore wind · 200 MW · withdrawn
- Solar project GI-69, Kingfisher CountySolar · 105 MW · withdrawn
- Onshore wind project GEN-2008-107, Kingfisher CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project GEN-2008-106, Kingfisher CountyOnshore wind · 100 MW · withdrawn
- Solar project GEN-2017-238, Kingfisher CountySolar · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem