United States › Grid › Interconnection queues › Montana
ONSHORE WIND · WESTOnshore wind project 418, Wheatland County
Onshore wind project 418, Wheatland County is a 750 MW onshore wind request in interconnection study in the West interconnection queue, in Wheatland County, Montana, connecting to NorthWestern Energy.
- PlanningQueued Jan 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 418
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- New proposed 500kV Substation between Broadview and Townsend
- Location
- Wheatland County, Montana
- Technology
- Wind: 750 MW
- Total requested
- 750 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study 12/12/2022
- Queue status
- Active
- Entered queue
- 10 January 2022
- Proposed online date
- October 2026
Location
Marker shows the centre of Wheatland County; the queue data does not give exact sites.
Other requests in Wheatland County
- Onshore wind project C012, Wheatland CountyOnshore wind · 750 MW · in study
- Onshore wind project C006, Wheatland CountyOnshore wind · 600 MW · in study
- Onshore wind project 361, Wheatland CountyOnshore wind · 600 MW · in study
- Onshore wind project 408, Wheatland CountyOnshore wind · 326 MW · in study
- Solar + storage project 432, Wheatland CountySolar + storage · 50.0 MW · in study
- Solar + storage project 431, Wheatland CountySolar + storage · 50.0 MW · in study
- Solar + storage project 417, Wheatland CountySolar + storage · 50.0 MW · in study
- Onshore wind project 362, Wheatland CountyOnshore wind · 300 MW · suspended
- Onshore wind project 360, Wheatland CountyOnshore wind · 200 MW · suspended
- Wind + storage project 347, Wheatland CountyWind + storage · 140 MW · suspended
- Wind + storage project 335, Wheatland CountyWind + storage · 80.0 MW · suspended
- Onshore wind project 4, Wheatland CountyOnshore wind · 135 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem