United States › Grid › Interconnection queues › Montana
WIND + STORAGE · WESTWind + storage project 335, Wheatland County
Wind + storage project 335, Wheatland County is a 80.0 MW wind + storage request suspended in the West interconnection queue, in Wheatland County, Montana, connecting to NorthWestern Energy.
Queue statusPaused / redesign
- PlanningQueued Sep 2017 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 335
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- 230kV Line from Judith Gap Auto to Judith Gap South
- Location
- Wheatland County, Montana
- Technology
- Wind: 80.0 MW · Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study System Impact Study Facilities Study
- Queue status
- Suspended
- Entered queue
- 25 September 2017
- Proposed online date
- October 2024
Location
Marker shows the centre of Wheatland County; the queue data does not give exact sites.
Other requests in Wheatland County
- Onshore wind project 418, Wheatland CountyOnshore wind · 750 MW · in study
- Onshore wind project C012, Wheatland CountyOnshore wind · 750 MW · in study
- Onshore wind project C006, Wheatland CountyOnshore wind · 600 MW · in study
- Onshore wind project 361, Wheatland CountyOnshore wind · 600 MW · in study
- Onshore wind project 408, Wheatland CountyOnshore wind · 326 MW · in study
- Solar + storage project 432, Wheatland CountySolar + storage · 50.0 MW · in study
- Solar + storage project 431, Wheatland CountySolar + storage · 50.0 MW · in study
- Solar + storage project 417, Wheatland CountySolar + storage · 50.0 MW · in study
- Onshore wind project 362, Wheatland CountyOnshore wind · 300 MW · suspended
- Onshore wind project 360, Wheatland CountyOnshore wind · 200 MW · suspended
- Wind + storage project 347, Wheatland CountyWind + storage · 140 MW · suspended
- Onshore wind project 4, Wheatland CountyOnshore wind · 135 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem