United States › Grid › Interconnection queues › Montana

WIND + STORAGE · WEST

Wind + storage project 347, Wheatland County

Wind + storage project 347, Wheatland County is a 140 MW wind + storage request suspended in the West interconnection queue, in Wheatland County, Montana, connecting to NorthWestern Energy.

Queue statusPaused / redesign
  1. PlanningQueued Jul 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
347
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
230kV Line from Judith Gap Auto to Judith Gap South
Location
Wheatland County, Montana
Technology
Wind: 140 MW · Battery
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study Feasibility Re-Study System Impact Study Facilities Study Facilities Re-Study
Queue status
Suspended
Entered queue
9 July 2018
Proposed online date
October 2024

Location

Marker shows the centre of Wheatland County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Wheatland County