United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTSitges Wind
Sitges Wind is a 600 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Motley County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0017
- Grid region
- ERCOT (Texas)
- Developer
- NextEra Energy Interconnection Holdings, LLC
- Connection point (POI)
- Tap 345kV 59904 Cottonwood–60500 Edith Clarke
- Location
- Motley County, Texas
- Technology
- Wind: 600 MW
- Total requested
- 600 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 22 March 2024
- Proposed online date
- January 2029
Location
Marker shows the centre of Motley County; the queue data does not give exact sites.
Other requests in Motley County
- Buzios SolarSolar + storage · 252 MW · agreement signed
- Collier Ranch SolarSolar · 253 MW · suspended
- Sitges Wind 2Onshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2006-025, Motley CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2005-015, Motley CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2008-121, Motley CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2008-041, Motley CountyOnshore wind · 135 MW · withdrawn
- Buzios Solar - ADD ADDITIONAL MW CAPACITYSolar · 51.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem