United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Sitges Wind

Sitges Wind is a 600 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Motley County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0017
Grid region
ERCOT (Texas)
Developer
NextEra Energy Interconnection Holdings, LLC
Connection point (POI)
Tap 345kV 59904 Cottonwood–60500 Edith Clarke
Location
Motley County, Texas
Technology
Wind: 600 MW
Total requested
600 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 March 2024
Proposed online date
January 2029

Location

Marker shows the centre of Motley County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Motley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem