United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTCollier Ranch Solar
Collier Ranch Solar is a 253 MW solar request suspended in the ERCOT interconnection queue, in Motley County, Texas.
Queue statusPaused / redesign
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0516
- Grid region
- ERCOT (Texas)
- Location
- Motley County, Texas
- Technology
- Solar: 253 MW
- Total requested
- 253 MW
- Queue status
- Suspended
- Entered queue
- 1 February 2024
Location
Marker shows the centre of Motley County; the queue data does not give exact sites.
Other requests in Motley County
- Buzios SolarSolar + storage Β· 252 MW Β· agreement signed
- Sitges WindOnshore wind Β· 600 MW Β· in study
- Sitges Wind 2Onshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2006-025, Motley CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2005-015, Motley CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2008-121, Motley CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2008-041, Motley CountyOnshore wind Β· 135 MW Β· withdrawn
- Buzios Solar - ADD ADDITIONAL MW CAPACITYSolar Β· 51.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem