OCTARY USA · INTERCONNECTION QUEUESSolar interconnection queue in the USA
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project G0678, Morrow County Solar |
1,200 MW | In study |
| Spectra Solar Solar · SE DC Devco |
1,200 MW | In study |
| Aurelius Solar Solar · IP Roman, LLC |
1,124 MW | Agreement signed |
| Pumpville Ranch 1 Solar |
1,000 MW | Paused / redesign |
| Solar project J4161, Watonwan County Solar |
1,000 MW | In study |
| Solar project Q274, Coconino County Solar |
1,000 MW | In study |
| Solar project AH2-351 Solar |
1,000 MW | In study |
| Solar project AH2-353 Solar |
1,000 MW | In study |
| Solar project G0687, Sherman County Solar |
900 MW | In study |
| Solar project J2186, Fulton County Solar |
821 MW | In study |
| Shadow Ranch Solar Solar · LectricWind LLC |
808 MW | In study |
| Blackwater Solar Solar |
800 MW | Agreement signed |
| Indigo Solar 3 Solar · Indigo solar 3 |
800 MW | In study |
| Blue Bird Solar Solar · Gigawatt Solar LLC |
773 MW | Agreement signed |
| Meitner Solar Solar · IP Meitner, LLC |
703 MW | Agreement signed |
| Solar project AH2-348, Daviess County Solar |
700 MW | In study |
| Solar project J2846, Pulaski County Solar |
700 MW | In study |
| Solar project J2261, Jackson County Solar |
625 MW | In study |
| Solar project J2262, Jackson County Solar |
625 MW | In study |
| Solar project IC-652, Sumter County Solar |
615 MW | Agreement signed |
| Skylab Solar Solar · EDF Renewables Development, Inc. |
610 MW | In study |
| Danish Fields Solar Solar · Danish Fields Solar, LLC |
603 MW | Agreement signed |
| Rocking X Solar Solar · 7100 Tin Top LLC |
602 MW | In study |
| Scorpius Solar Solar · Ben Milam Solar 4 |
600 MW | In study |
| Solar project G0669, Crook County Solar |
600 MW | In study |
| Solar project J2477, Crittenden County Solar |
600 MW | In study |
| Solar project G0539, Deschutes County Solar |
600 MW | Agreement signed |
| Solar project J2519, Richland Parish County Solar |
600 MW | In study |
| Solar project G0673, Crook County Solar |
600 MW | In study |
| Capoterra Solar |
598 MW | Paused / redesign |
| Brittlebush Solar Solar |
594 MW | Paused / redesign |
| Jenna Eco-Electric Solar Solar · Clean Energy Holdings, LLC |
576 MW | In study |
| Soledad Solar Solar |
562 MW | In study |
| Sanborn 5 Hybrid Solar |
560 MW | Agreement signed |
| Domestic Chicken Solar |
559 MW | In study |
| Solar project J2478, Craighead County Solar |
550 MW | In study |
| Solar project J4102, Cass County Solar |
539 MW | In study |
| Renegade Project Solar · Renegade Renewable LLC |
516 MW | Agreement signed |
| Point Mountain Solar Solar |
514 MW | Paused / redesign |
| La Salle Solar Solar · La Salle Solar LLC |
513 MW | Agreement signed |
| Half Moon Solar Solar · NextEra Energy Interconnection Holdings, LLC |
513 MW | Agreement signed |
| Solar project GEN-2021-030, Linn County Solar |
510 MW | In study |
| Velveteen Solar I Solar · Velveteen Solar, LLC |
509 MW | In study |
| Bayside Solar Solar |
509 MW | Paused / redesign |
| Torbino Solar Solar |
507 MW | In study |
| Tabor Solar Solar · Quanah Solar LLC |
506 MW | In study |
| Big Field Solar Solar · Big Field Solar Energy LLC |
506 MW | In study |
| Muy Grande Solar Solar · ACE DevCo NC, LLC |
503 MW | In study |
| Dog Star Solar II Solar · Dog Star Solar LLC |
503 MW | In study |
| Dog Star Solar I Solar · Dog Star Solar LLC |
503 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)747 · 133.2 GW
- ERCOT (Texas)417 · 96.8 GW
- PJM (Mid-Atlantic, Midwest)730 · 59.8 GW
- Southeast (non-ISO utilities)544 · 51.6 GW
- SPP (Southwest Power Pool)193 · 37.7 GW
- West (non-ISO utilities)240 · 34.1 GW
- NYISO (New York)72 · 6,628 MW
- CAISO (California)25 · 6,355 MW
- ISO-NE (New England)27 · 1,425 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)