United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTPoint Mountain Solar
Point Mountain Solar is a 514 MW solar request suspended in the ERCOT interconnection queue, in Upton County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jul 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0049
- Grid region
- ERCOT (Texas)
- Location
- Upton County, Texas
- Technology
- Solar: 514 MW
- Total requested
- 514 MW
- Queue status
- Suspended
- Entered queue
- 17 July 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Upton County; the queue data does not give exact sites.
Other requests in Upton County
- McCamey's Castle BatteryBattery storage Β· 410 MW Β· agreement signed
- Larkspur Energy StorageBattery storage Β· 308 MW Β· agreement signed
- Grandfalls SolarSolar + storage Β· 176 MW Β· agreement signed
- West Royal Natural Gas (TEF-Due Diligence)Gas Β· 888 MW Β· in study
- Shadow Ranch SolarSolar Β· 808 MW Β· in study
- Tres Rios Ranch SolarSolar + storage Β· 508 MW Β· in study
- WindeckerOnshore wind Β· 420 MW Β· in study
- BRP Aras BESSBattery storage Β· 304 MW Β· in study
- Badger SolarSolar + storage Β· 302 MW Β· in study
- Vista Bluff Wind II "Alternate POI"Onshore wind Β· 290 MW Β· in study
- Vista Bluff Wind I "Alternate POI"Onshore wind Β· 290 MW Β· in study
- Tres Rios Ranch BESSSolar + storage Β· 290 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem