BATTERY STORAGE · ERCOT

BRP Aras BESS

BRP Aras BESS is a 304 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Upton County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0272
Grid region
ERCOT (Texas)
Developer
BRP Aras BESS LLC
Connection point (POI)
76595 North McCamey 138kV
Location
Upton County, Texas
Technology
Battery: 304 MW
Total requested
304 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
31 May 2021
Proposed online date
December 2028

Location

Marker shows the centre of Upton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Upton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem