πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Bayside Solar

Bayside Solar is a 509 MW solar request suspended in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Feb 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0189
Grid region
ERCOT (Texas)
Location
Victoria County, Texas
Technology
Solar: 509 MW
Total requested
509 MW
Queue status
Suspended
Entered queue
8 February 2021
Proposed online date
August 2026

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Victoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem