BATTERY STORAGE · ERCOT

Brizo BESS

Brizo BESS is a 141 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2021 (completed)
  2. ConsentedMar 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0342
Grid region
ERCOT (Texas)
Developer
BRP Brizo BESS LLC
Connection point (POI)
138 kV Loop 463 Substation (#5680)
Location
Victoria County, Texas
Technology
Battery: 141 MW
Total requested
141 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
5 October 2021
Agreement signed
27 March 2025
Proposed online date
December 2027

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Victoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem