Oriana BESS

Oriana BESS is a 60.3 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2021 (completed)
  2. ConsentedFeb 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0109
Grid region
ERCOT (Texas)
Developer
Oriana Solar LLC
Connection point (POI)
Tap 138kV 5502 Rayburn - 5584 Vanderbilt
Location
Victoria County, Texas
Technology
Battery: 60.3 MW · Battery
Total requested
60.3 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
25 August 2021
Agreement signed
27 February 2023
Proposed online date
October 2028

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Victoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem