United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

HyFuels Calhoun Solar

HyFuels Calhoun Solar is a 302 MW solar request in interconnection study in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0028
Grid region
ERCOT (Texas)
Developer
HyFuels Green Lake Solar LLC
Connection point (POI)
Tap 345kV 8715 RADIANT7A - 8728 COBRA7A
Location
Victoria County, Texas
Technology
Solar: 302 MW
Total requested
302 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
18 October 2022
Proposed online date
October 2027

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Victoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem