Solar project J2519, Richland Parish County

Solar project J2519, Richland Parish County is a 600 MW solar request in interconnection study in the MISO interconnection queue, in Richland Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2519
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Smalling
Location
Richland Parish County, Louisiana
Technology
Solar: 600 MW
Total requested
600 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 September 2022
Proposed online date
October 2026

Location

Marker shows the centre of Richland Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Richland Parish County