United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR Β· MISOSolar project J1995, Richland Parish County
Solar project J1995, Richland Parish County is a 180 MW solar request withdrawn in the MISO interconnection queue, in Richland Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1995
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- DUNN - OAK RIDGE (LA) 115.0kV
- Location
- Richland Parish County, Louisiana
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 4 August 2021
- Proposed online date
- July 2025
- Withdrawn
- March 2025
Location
Marker shows the centre of Richland Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Richland Parish County
- Richland Parish generatorsGas Β· 1,640 MW Β· in study
- Richland Parish generatorsGas Β· 1,640 MW Β· in study
- Franklin FarmsGas Β· 1,640 MW Β· in study
- Solar project J2519, Richland Parish CountySolar Β· 600 MW Β· in study
- Solar + storage project J2838, Richland Parish CountySolar + storage Β· 150 MW Β· in study
- Gas project J3842, Richland Parish CountyGas Β· 770 MW Β· withdrawn
- Gas project J3841, Richland Parish CountyGas Β· 770 MW Β· withdrawn
- Solar project J3760, Richland Parish CountySolar Β· 405 MW Β· withdrawn
- Solar project J1133, Richland Parish CountySolar Β· 100 MW Β· withdrawn
- Solar project J919A, Richland Parish CountySolar Β· 100 MW Β· withdrawn
- Solar project J660, Richland Parish CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem