SOLAR Β· ERCOT

Capoterra

Capoterra is a 598 MW solar request suspended in the ERCOT interconnection queue, in Milam County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0087
Grid region
ERCOT (Texas)
Location
Milam County, Texas
Technology
Solar: 598 MW
Total requested
598 MW
Queue status
Suspended
Entered queue
16 June 2022

Location

Marker shows the centre of Milam County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Milam County