Stoneridge Solar

Stoneridge Solar is a 202 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Milam County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2021 (completed)
  2. ConsentedMay 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0031
Grid region
ERCOT (Texas)
Developer
Stoneridge Solar, LLC
Connection point (POI)
Tap 345 kV 13429 SANDOW SWITCH - 7040 AUSTROP Beulah Switch to tap above line
Location
Milam County, Texas
Technology
Solar: 202 MW
Total requested
202 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
8 October 2021
Agreement signed
15 May 2023
Proposed online date
April 2026

Location

Marker shows the centre of Milam County; the queue data does not give exact sites.