United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 1 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G1053, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Battery storage project G1055, Wasco County
Battery storage
1,300 MWIn study Wasco, ORWest Nov 2023target 2032
Battery storage project G1054, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Battery storage project G0608, Klickitat County
Battery storage
1,200 MWIn study Klickitat, WAWest Dec 2018target 2027
Pion
Battery storage
1,168 MWIn study Fresno, CACAISO Apr 2023target 2028
Battery storage project AI2-457, Charles County
Battery storage
1,122 MWIn study Charles, MDPJM Mar 2023target 2027
Hillside Energy Storage
Battery storage
1,065 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Crusade
Battery storage
1,029 MWIn study Orange, CACAISO Apr 2023target 2028
Lagoonez
Battery storage
1,029 MWIn study Los Angeles, CACAISO Apr 2023target 2028
Kickstart Energy Storage VI
Battery storage · Kickstart Infrastructure LLC
1,026 MWIn study Ellis, TXERCOT Dec 2025target 2029
Battery storage project Q2405, Maricopa County
Battery storage
1,020 MWIn study Maricopa, AZWest Feb 2024target 2033
Battery storage project G0914, Douglas County
Battery storage
1,000 MWIn study Douglas, WAWest Jul 2023target 2028
Battery storage project Q468, Maricopa County
Battery storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Battery storage project Q112, San Bernardino County
Battery storage
1,000 MWIn study San Bernardino, CAWest Oct 2024target 2028
Kickstart Energy Storage V
Battery storage · Kickstart Infrastructure LLC
999 MWIn study Ellis, TXERCOT Nov 2025target 2029
Battery storage project Company 257, Clark County
Battery storage
800 MWIn study Clark, NVWest Sep 2023target 2026
Irving Storage
Battery storage
783 MWAgreement signed Monterey, CACAISO May 2019target 2025
Nabla Energy Storage I
Battery storage · Nabla Park LLC
750 MWIn study Tarrant, TXERCOT Nov 2025target 2028
Nabla Energy Storage II
Battery storage · Nabla Park LLC
750 MWIn study Parker, TXERCOT Nov 2025target 2028
Menifee Power Bank
Battery storage
680 MWAgreement signed Riverside, CACAISO Apr 2019target 2025
Steel City Battery Storage
Battery storage
675 MWAgreement signed Contra Costa, CACAISO Apr 2020target 2029
Battery storage project AH1-716, James City County
Battery storage · Cardinal Energy Storage East, LLC
650 MWIn study James City, VAPJM Apr 2025
Battery storage project G1056, Deschutes County
Battery storage
650 MWIn study Deschutes, ORWest Nov 2023target 2030
Battery storage project G0963, Morrow County
Battery storage
650 MWIn study Morrow, ORWest Oct 2023target 2030
Battery storage project G0948, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0947, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0796, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Battery storage project G0778, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Aug 2022target 2027
Battery storage project G0965, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Oct 2023target 2032
Battery storage project G0774, Wasco County
Battery storage
650 MWIn study Wasco, ORWest Aug 2022target 2028
Battery storage project G0946, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0792, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Yuha Desert Battery Storage
Battery storage
633 MWIn study Imperial, CACAISO Apr 2021target 2031
Malden BESS
Battery storage · NIPSCO
630 MWIn study Porter, INMISO Aug 2025target 2027
Howard Road BESS
Battery storage · Project Fast Flow LLC
618 MWIn study Bexar, TXERCOT Jul 2025target 2028
Comanche BESS
Battery storage · ENERGOS BESS
614 MWIn study Comanche, TXERCOT Dec 2024target 2028
Symphony BESS
Battery storage · Symphony BESS, LLC
612 MWIn study Austin, TXERCOT Feb 2025target 2028
Lavita BESS
Battery storage · Lavita BESS, LLC
606 MWIn study Bell, TXERCOT Dec 2024target 2028
Hobby BESS I
Battery storage · Airport Storage II LLC
603 MWIn study Harris, TXERCOT Sep 2024target 2027
Battery storage project G0807, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Battery storage project G0642, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2025
Tempesta BESS
Battery storage
600 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Capoterra BESS
Battery storage
600 MWPaused / redesign Milam, TXERCOT Jun 2022
Battery storage project G0812, Lane County
Battery storage
600 MWIn study Lane, ORWest Sep 2022target 2030
Battery storage project 622, Malheur County
Battery storage · Owyhee Energy Storage, LLC
600 MWAgreement signed Malheur, ORWest Oct 2021target 2029
Battery storage project IC-974, Fulton County
Battery storage
600 MWPaused / redesign Fulton, GASoutheast Jul 2021target 2025
Battery storage project 25-IC-1374, Hancock County
Battery storage
600 MWIn study Hancock, GASoutheast Apr 2025target 2029
Battery storage project G0808, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Page 1 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)