BATTERY STORAGE Β· ERCOTCapoterra BESS
Capoterra BESS is a 600 MW battery storage request suspended in the ERCOT interconnection queue, in Milam County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jun 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0088
- Grid region
- ERCOT (Texas)
- Location
- Milam County, Texas
- Technology
- Battery: 600 MW
- Total requested
- 600 MW
- Queue status
- Suspended
- Entered queue
- 16 June 2022
Location
Marker shows the centre of Milam County; the queue data does not give exact sites.
Other requests in Milam County
- Sypert Branch Solar ProjectSolar Β· 261 MW Β· agreement signed
- Eastbell Milam SolarSolar Β· 245 MW Β· agreement signed
- Adelite StorageBattery storage Β· 232 MW Β· agreement signed
- Hoyte SolarSolar Β· 207 MW Β· agreement signed
- Stoneridge SolarSolar Β· 202 MW Β· agreement signed
- Yaupon Solar SLFSolar Β· 201 MW Β· agreement signed
- Camino Santiago SolarSolar Β· 196 MW Β· agreement signed
- Dos Rios Energy Storage SLFBattery storage Β· 165 MW Β· agreement signed
- Eastbell Milam Solar IISolar Β· 151 MW Β· agreement signed
- Happy Dog StorageSolar + storage Β· 105 MW Β· agreement signed
- Stoneridge BESSBattery storage Β· 102 MW Β· agreement signed
- HappyDogSolarSolar + storage Β· 85.5 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem