🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

BATTERY STORAGE · WEST

Battery storage project G0608, Klickitat County

Battery storage project G0608, Klickitat County is a 1,200 MW battery storage request in interconnection study in the West interconnection queue, in Klickitat County, Washington.

Queue statusIn planning
  1. PlanningQueued Dec 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0608
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's John Day 500 kV Substation
Location
Klickitat County, Washington
Technology
Battery: 1,200 MW
Total requested
1,200 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
7 December 2018
Proposed online date
December 2027

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Klickitat County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem