ONSHORE WIND · WEST

Onshore wind project G0585, Klickitat County

Onshore wind project G0585, Klickitat County is a 313 MW onshore wind request in interconnection study in the West interconnection queue, in Klickitat County, Washington.

Queue statusIn planning
  1. PlanningQueued Mar 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0585
Grid region
West (non-ISO utilities)
Connection point (POI)
McNary-John Day 500kV Tap (BPA's "G0585 Substation")
Location
Klickitat County, Washington
Technology
Wind: 313 MW
Total requested
313 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
19 March 2018
Proposed online date
July 2021

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Klickitat County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem